RED I - PLEASANT GROVE
INVESTOR UPDATE | MARCH 2026
Thank you for your continued partnership in the PG Development project. We are pleased to report that all horizontal underground infrastructure — including sewer, gas, and water — has been successfully completed. The project is now advancing through final site finishing work, with curb and gutter installation and asphalt paving on the near-term horizon. These milestones position us to begin vertical construction of the twin homes in May 2026.
Your ongoing support has enabled us to maintain project momentum and execute efficiently through the infrastructure phase. We remain committed to transparent communication and provide this detailed progress update as we transition toward the construction phase.
KEY ACCOMPLISHMENTS
RECENT
Full city approval maintained
All municipal requirements continue to be satisfied, keeping the project on track for construction activities.
All underground infrastructure completed
Sewer, gas, and water installation have been fully completed across the development site.
Value engineering completed
House plans have been optimized to increase unit sizes to over 2,000 square feet while maintaining cost efficiency.
Construction timeline updated
Detailed project schedule updated with our general contractor and builder partner, with vertical construction targeted to begin in May 2026.
PRIMARY FOCUS AREAS
CURRENT
Curb and gutter installation
Curb and gutter work is scheduled to be completed by early April, marking a key step in final site preparation.
Vertical construction preparation
All preparations are advancing to begin twin home construction in May 2026, transitioning the project from infrastructure to building.
Asphalt paving
Following curb and gutter completion, asphalt paving is expected by mid-April, completing the horizontal improvements phase.
MAJOR MILESTONES
NEXT
Curb and gutter installation: Early April 2026
Asphalt paving: Mid-April 2026
Vertical construction commencement: May 2026
First units available: Q4 2026
Nearby Community Amenity
Completion of Cook Family Park
We are pleased to announce the completion of Cook Family Park, located just a couple blocks from the Pleasant Grove development. This beautiful new green space serves as a significant enhancement to the local neighborhood.
Enhanced Walkability
Future residents will enjoy immediate access to recreational trails and open space, encouraging an active, pedestrian-friendly lifestyle.
Community & Property Value
The proximity of this high-quality park is a key differentiator, significantly increasing the long-term desirability and appeal of our development to prospective homeowners.
Elevated Quality of Life
This project reinforces our commitment to building in areas that offer superior lifestyle amenities, creating a vibrant environment for the families who will live here.
LOOKING FORWARD
With all underground infrastructure now in place, the project team is focused on completing the remaining horizontal site work. Curb and gutter installation is expected by early April, followed by asphalt paving by mid-April.
These final site improvements will clear the path for vertical construction of the twin homes, which we anticipate beginning in May 2026. We are targeting completion of the first units in Q4 2026.
As always, we remain committed to efficient project execution and will continue providing regular updates on our progress.

This update reflects project status as of March 2026. For specific questions or additional information, please contact the project management team.